What will be followed below is the work description of a company which has
Can be mention From 2003 to 2007 Energy Peyman has had simultaneous
participation in major projects in phase 1of South Pars petrochemical area.
ACTIVITY LIST, Scope of Electrical:
- Panel installation for power LV- MV-MCC-Switch gear
(Energy Peyman Co.=EPCo.) is a registered contractor as rated 3 for "Power" & 3
for "Industrial Equipment" and 5 for "Civil" & “Industry & Mine”. EPCo has got its
ISO 9001:2008 in engineering and procurement and construction for industrial
projects from URS:UKAS, England. EPCo is member of society of engineering &
contractor company for oil & gas & petrochemy companies.EPCo. As a technical
and engineering company to exeute huge projects, is committed to quality rules
and follows below mentioned goals during executing projects:
1. Precise control of different steps of projects based on time scheduled activity
2. Continuous effort to increase clients satisfactions.
3. To obey the internationals and local laws and standards.
4. Continuous human resource training.
Photo 19
Photo 20
Photo 21
Photo 22
Photo 23
Photo 24
Project: Installation of return vapor compressors and related accessories
Project: Bid Boland II Behbahan Petrochemical company.
Project: All Electrical, Control and Instrumentation systems and Telecom
Project: Bid Boland II Behbahan Petrochemical company.
Water research institute:
Procurement, installation, commissioning of river over flow detecting
O.I.E.C (RAMSHIR):
Installation and Pre Commissioning of electrical and instrument of Phase
A.Z.A.A.N CONSORTIUM – Installation of electrical and instrument of
Offsite Lines of Petrochemical Zone ( Mobin Petrochemical Company),
MEAM TEAM –ASFALT TOUS CONSORTIUM: Installation of Heavy Equip-
ments, Furnaces and Pumps and Installation of Refractory of Incineration
RAMSHIR C.T.C. Installation of electrical and instrument of 10Th Olefins (
Main Unit of Jam Petrochemical ) In South Pars Special Economic Zone
SEPAH MARINE CORPS – EPC (Engineering, procurement and construction
of buildings, tanks, piping and other works of sepah marine corps station /
SHAHID TAHERI STORE (N.I.G.C) EPC (Engineering, procurement and
construction of All electrical work / SAVEH ) (1995 -1994)
Project: Nouri (Previously Borzouyeh) Petrochemical Company.
Phase 9&10 South pars-Area C-Train no -1JB Installation
Phase 9&10 South pars-Area C-Train no -1LCB control station
Phase 9&10 South pars-Area C-Train no -1LCB control station
Phase 9&10 South pars-Area C-Post NO -6 transformer 11/33 kv
Phase 9 & 10 South pars - Area C - LV Post NO 6
Phase 9&10 South pars-Area C-LV Post NO -6 Dry transformer
Phase 9 & 10 South pars - Area C - LV Post NO 6 - battery room
Phase 9&10 South pars-Area C-LV Post NO -6
Phase 9&10 South pars-Area C-Train no -1LCB control station
Phase 9&10 South pars-Area C-Post NO -6
Cabling and tray installation for main train
Phase 9&10 South pars-Area C-earth bar and
earth connection to main train pipe rack
Phase 9&10 South pars-Area C-Post NO -6 transformer 11/33 kv
Phase 9&10 South pars-Area C-Post NO -6 transformer 0.4/6 kv and bus duct
Phase 9&10 South pars-Area C-Post NO -6
Phase 9&10 South pars-Area C-LV Post NO -6HV panel
switch gear test and start up
Phase 9&10 South pars-Area C-Post NO -6
Cabling and tray installation for main train
Phase 9&10 South pars-Area C-analizer room -train NO 1
Phase 9&10 South pars-Area C-valve calibration shop
Phase 9&10 South pars- Special store area for cable drums
Phase 9&10 South pars-Area C-LV Post NO -6HV panel cable connection
Installation of Cable Ladder and Cable Pulling (with Scaffolding)
(Substation 6, Area C, Phase 10&9, Gas Plant)
Phase 9&10 South pars -area lighting
Phase 9&10 South pars-Area C-control room NO 8
Phase 9&10 South pars -area lighting
Installation of Cable Ladder and Cable Pulling (with Scaffolding)
(Substation 6, Area C, Phase 10&9, Gas Plant)
Phase 9&10 South pars -area lighting
Phase 9&10 South pars-Area C-control room NO 8
Phase 9&10 South pars-Area C-PG Canduit pipng
Phase 9&10 South pars-Area C-Post NO -6
Cabling and tray installation for main train
Installation of Bag Filter Ducts (Incineration Plant MOBIN Utility Complex)
Installation of Ducts (Incineration Plant MOBIN Utility Complex)
Installation of Pumps (Incineration Plant - MOBIN Utility Complex)
Installation of Fire Water Diesel Pump
Water Center Substation- MOBIN Petrochemical Co.
Stacks , Bag Filters Incineration Plant - MOBIN Utility Complex
Installation of Refractory (Incineration Plant MOBIN Utility Complex)
Installation of Bag Filters Incineration Plant MOBIN Utility Complex
Electrical & Instrument Control System Tabriz Petrochemical Co.
Installation of Gas Control Detection Tabriz Petrochemical
Installation of Equipment Arak Petrochemical Co.
Laying of Electrical Cables Arak Petrochemical Co.
(Zone Building Pump Station – Mobin Petrochemical Co.)
Alignment of Fire water Pump Mobin Petrochemical Co.
Finalize of Electrical Pumps Mobin Petrochemical Co
Alignment of Fire water Pump Mobin Petrochemical Co.
Stack Unit 57 Incineration Plant - MOBIN Utility Complex
Fabrication of Tanks Incineration Plant - MOBIN Utility Complex
Electrical & Instrument works Arak Petrochemical Co.
Stack Unit 57 Incineration Plant - MOBIN Utility Complex
Stack Unit 57 Incineration Plant - MOBIN Utility Complex
Stack Unit 57 Incineration Plant - MOBIN Utility Complex
installation & setting of control valves
METAL WORK & PIPE RACK
HEAT TRACING OF TRAIN 1, AREA C, PHAZE 10 & 9 SOUTH PARS
HEAT TRACING OF TRAIN 1, AREA C, PHAZE 10 & 9 SOUTH PARS
HEAT TRACING OF TRAIN 1, AREA C, PHAZE 10 & 9 SOUTH PARS
HEAT TRACING OF INSTRUMENT & PIPES, TRAIN 2,
AREA C, PHAZE 10 & 9 SOUTH PARS
calibration of safety & relief valves
Vaccume Dead Weight Tester
Portable Pressure Calibrators
Pressure Gauge Calibration
Pressure Dead Weith Tester
4.5 Digit Multi Meter With High Voltage Probe
Disturtion Analyzer
Frequency And Power Measurement & Generation
Calibration Of Multi-Process Calibrature Vs 8.5 Digit Refrence Multimeter
Energy Peyman's Engeeniring Office At South Pars (Assalouyeh)
Energy Peyman's Engeeniring Camp At South Pars (Assalouyeh)
Calibration Of PRT Sencore With SPRT Sencore On Liqude Bath
Themprature Bath
Energy Peyman's Engeeniring Office At South Pars (Assalouyeh)